Like a lot of countries, India wants the best weapons it can afford. But ideological and financial concerns mean there are a lot of things it won’t buy from the United States or Europe. That pretty much leaves, well, Russia.

India has been a big buyer of Russian weapons for 50 years. Those haven’t been easy years for New Delhi. India’s defense contracts with Russia have consistently suffered delays and cost overruns. And the resulting hardware doesn’t always work.

Of all India’s Russian procurement woes, none speak more to the dysfunctional relationship between the two countries than the saga of INS Vikramaditya. In the early 2000s, India went shopping for a new aircraft carrier. What followed was a military-industrial nightmare.

Wanted—One New(ish) Carrier

In 1988, the Soviet Union commissioned the aircraft carrier Baku. She and her four sisters of the Kiev class represented a unique Soviet design. The front third resembled a heavy cruiser, with 12 giant SS-N-12 anti-ship missiles, up to 192 surface-to-air missiles and two 100-millimeter deck guns. The remaining two-thirds of the ship was basically an aircraft carrier, with an angled flight deck and a hangar.

Baku briefly served in the Soviet navy until the USSR dissolved in 1991. Russia inherited the vessel, renamed her Admiral Gorshkov and kept her on the rolls of the new Russian navy until 1996. After a boiler room explosion, likely due to a lack of maintenance, Admiral Gorshkov went into mothballs.

In the early 2000s, India faced a dilemma. The Indian navy’s only carrier INS Viraat was set to retire in 2007. Carriers help India assert influence over the Indian Ocean—not to mention, they’re status symbols. New Delhi needed to replace Viraat, and fast.

India’s options were limited. The only countries building carriers at the time—the United States, France and Italy—were building ships too big for India’s checkbook. In 2004, India and Russia struck a deal in which India would receive Admiral Gorshkov. The ship herself would be free, but India would pay $974 million dollars to Russia to upgrade her.

More from War Is Boring

Don’t Call This Ship an Aircraft Carrier

China’s Third Aircraft Carrier Could Be Nuclear

American Aircraft Carriers Will Peak in 2024

It was an ambitious project. At 44,500 tons, Admiral Gorshkov was a huge ship. Already more than a decade old, she had spent eight years languishing in mothballs. Indifference and Russia’s harsh winters are unkind to idle ships.

Russia would transform the vessel from a helicopter carrier with a partial flight deck to an aircraft carrier with a launch ramp and a flight deck just over 900 feet long. She would be capable of supporting 24 MiG-29K fighters and up to 10 Kamov helicopters.

She would have new radars, new boilers for propulsion, new arrester wires for catching landing aircraft and new deck elevators. All 2,700 rooms and compartments—spread out over 22 decks—would be refurbished and new wiring would be laid throughout the ship. The “new” carrier would be named Vikramaditya, after an ancient Indian king.

A real aircraft carrier for less than a billion dollars sounds almost too good to be true. And it was.

Shakedown

In 2007, just a year before delivery, it became clear that Russia’s Sevmash shipyard couldn’t meet the ambitious deadline. Even worse, the yard demanded more than twice as much money—$2.9 billion in total—to complete the job.

The cost of sea trials alone, originally $27 million, ballooned to a fantastic $550 million.

A year later, with the project still in disarray, Sevmash estimated the carrier to be only 49-percent complete. Even more galling, one Sevmash executive suggested that India should pay an additional $2 billion, citing a “market price” of a brand-new carrier at “between $3 billion and $4 billion.”

For its part, Sevmash claimed that the job was proving much more complicated than anyone had ever imagined. Nobody had tried converting a ship into an aircraft carrier since World War II.

Sevmash specialized in submarine construction and had never worked on an aircraft carrier before. The ship had been originally built at the Nikolayev Shipyards, which after the breakup of the Soviet Union became part of the Ukraine. The tooling and specialized equipment used to build Admiral Gorshkov was thousands of miles away and now in a foreign country.